Centro Nuoto Mirandola

Mirandola, Italy

Benchmark of the community of Mirandola, the Mirandola Acquatic Center was completely renewed through a Public Private Partnership operation.

According to the call for tenders of the public administration, the project team MIRAMAR, made of Bottoli Constructions, A&T Europe-Myrtha Pools and the managing entity Coopernuoto, redesigned and expanded the building, increasing the number of services offered to the guests.

The result of the refurbishment is a high architectural value facility, designed with new swimming pool filtration systems and upgraded to ensure energy efficiency.

 

Two indoor pools – a 8-lanes 25 m pool and a 3-lanes teaching pool – were renovated by using RenovAction technology.

 

In the wellness area of Mirandola Acquatic Center, Myrtha Pools also installed a steam room, sensory showers and a Spa pool, equipped with hydromassage benches and fountains, where guests can enjoy the hydrotherapy benefits.

 

In the outdoor area, the olympic pool was totally redesigned to meet the new needs of the community. The pool now includes children and adults dedicated acquatic areas: a lagoon with a shallow beach entry for the babies; a relaxing area with hydro-massage, for guests of all ages. Last but not least, a swimming area and a pool with waterslides and water toys for the thrill of the whole family.

 

The Center is completed by the new reception and the renovated bar area at the entrance, not to mention the redeveloped locker rooms and the grandstands near the large pool.

Equipped with all the best competition accessories such as the exclusive starting blocks Myrtha Track Start and the footrest wedge Myrtha Backstroke System, this acquatic center fulfills athletes, sports lover and families.

Despite high complexity and issues linked to building improvement, it took just 9 months to finish all the costruction works, respecting the original budget.

 

Acquatic Center Mirandola:

Type of operation: Project Financing

Intervention Value:           4.000.000 euros (taxes included)

Type of Intervention: Existing facility refurbishment

Finance: 3.000.000 euros Finincing SVP;  1.000.000 euros Equity

Other contributes: 325.000 euros/year Municipal contribution;  75.000 euros/year management rent paid by the SPV to the Municipal Administration

Benchmark of the community of Mirandola, the Mirandola Acquatic Center was completely renewed through a Public Private Partnership operation.

According to the call for tenders of the public administration, the project team MIRAMAR, made of Bottoli Constructions, A&T Europe-Myrtha Pools and the managing entity Coopernuoto, redesigned and expanded the building, increasing the number of services offered to the guests.

The result of the refurbishment is a high architectural value facility, designed with new swimming pool filtration systems and upgraded to ensure energy efficiency.

 

Two indoor pools – a 8-lanes 25 m pool and a 3-lanes teaching pool – were renovated by using RenovAction technology.

In the wellness area of Mirandola Acquatic Center, Myrtha Pools also installed a steam room, sensory showers and a Spa pool, equipped with hydromassage benches and fountains, where guests can enjoy the hydrotherapy benefits.

In the outdoor area, the olympic pool was totally redesigned to meet the new needs of the community. The pool now includes children and adults dedicated acquatic areas: a lagoon with a shallow beach entry for the babies; a relaxing area with hydro-massage, for guests of all ages. Last but not least, a swimming area and a pool with waterslides and water toys for the thrill of the whole family.

The Center is completed by the new reception and the renovated bar area at the entrance, not to mention the redeveloped locker rooms and the grandstands near the large pool.

Equipped with all the best competition accessories such as the exclusive starting blocks Myrtha Track Start and the footrest wedge Myrtha Backstroke System, this acquatic center fulfills athletes, sports lover and families.

Despite high complexity and issues linked to building improvement, it took just 9 months to finish all the costruction works, respecting the original budget.

Acquatic Center Mirandola:

Type of operation: Project Financing

Intervention Value:           4.000.000 euros (taxes included)

Type of Intervention: Existing facility refurbishment

Finance: 3.000.000 euros Finincing SVP;  1.000.000 euros Equity

Other contributes: 325.000 euros/year Municipal contribution;  75.000 euros/year management rent paid by the SPV to the Municipal Administration